Multiple UPS Scheme
ElectricalOM is capable of modelling multiple UPS components working in parallel. In order to model such a scheme, the user needs to follow the steps below:
- Right click on the UPS which will be run in parallel with the new UPS and select Install supply from... option.
- Select the same source as the selected UPS and click OK.
- Select Parallel source operation... option from the Functions Menu.
- Select the selected UPS from the list and click OK.
- Now, both switches will act together and the UPS will be indicated as 2x prefix. This means there are two units of the same UPS connected to the SB1.
- In order to add more UPS, the same procedure must be followed.